IV B.Tech I Semester Supplementary Examinations, February/March – 2018
SOFTWARE PROJECT MANAGEMENT (Common to Computer Science and Engineering and Information Technology)Time: 3 hours Max. Marks: 70
Question paper consists of Part-A and Part-B
Answer ALL sub questions from Part-A
Answer any THREE questions from Part-B
*****
PART ?A (22 Marks)1. a) Discuss need of software project management [4]
b) What is a Lifecycle Model of Project Management? [3]
c) Write about function point analysis. [4]
d) Write about Risk monitoring [4]
e) Discuss about recourse allocation in Project Management. [4]
f) Define Quality of software. [3]
PART ?B (3×16 = 48 Marks)2. a) Explain in detail various activities of software management [8]
b) List and Explain various Software Effort Estimation Techniques [8]
3. a) Explain the first two phases of the life-cycle process. [8]
b) Explain the typical minor milestones in the lifecycle of iteration. [8]
4. a) Explain in detail various steps in software project estimation [8]
b) Discuss in detail different models of COCOMO with an example [8]
5. Explain about
a) Risk Identification and
b) Risk Quantification [16]
6. What is earned value of a Project? Explain about earned value analysis. [16]
7. a) What is CMM? Explain the process of CMM with neat sketch. [8]
b) Discuss in detail about enhancing software quality. [8]
Code No: RT4105C
Set No. 1
R13
1 of 1
746268 PAPER V - REHABILITATION MEDICINE INCLUDING GERIATRIC MEDICINETHE TAMIL NADU DR. M.G.R. MEDICAL UNIVERSITY…
746268 PAPER V - REHABILITATION MEDICINE INCLUDING GERIATRIC MEDICINETHE TAMIL NADU DR. M.G.R. MEDICAL UNIVERSITY…
746267 PAPER IV - P.T. IN ORTHOPAEDICSTHE TAMIL NADU DR. M.G.R. MEDICAL UNIVERSITY [LN 6267]…
746267 PAPER IV - P.T. IN ORTHOPAEDICSTHE TAMIL NADU DR. M.G.R. MEDICAL UNIVERSITY [LN 6267]…
746266 PAPER III – CLINICAL ORTHOPAEDICSTHE TAMIL NADU DR. M.G.R. MEDICAL UNIVERSITY [LN 6266] AUGUST…
746265 PAPER II – P.T. IN NEUROLOGYTHE TAMIL NADU DR. M.G.R. MEDICAL UNIVERSITY [LN 6265]…